CONSOLIDATION OF MIRIAM GOLD TENURE ADJACENT TO
FORREST AND THE MIRIAM SHEAR
Ore Resources Ltd (ASX: OR3) (Ore or the Company) is pleased to advise that it has entered into a binding option
agreement (Agreement) to acquire additional tenure at its 100%-owned Miriam Gold Project (Miriam), part of
the Company’s Coolgardie Gold Projects located in the Eastern Goldfields of Western Australia.
HIGHLIGHTS
• Ore has executed a binding option agreement to acquire six (6) tenements, comprising four (4) mining
leases, one prospecting licence application, and one special prospecting licence application adjacent to
its current landholdings at Miriam.
• Completion of the agreement will result in further consolidation of Miriam and enhances gold
exploration potential along the 6.2km-long Miriam Shear Zone (Miriam Shear).
• Two mining leases (M15/1255 and M15/1819) located immediately east of, and adjacent to, the
Forrest prospect (Forrest), enabling step-out drilling to to test extensions of the mineralised gold
system and identify linking structures across the expanded tenure.
• Historical drilling at M15/1255 defined a 300m long mineralised trend at the Devils Playground
Prospect (Devils Playground) on the eastern flank of the Miriam Shear.
• Key historical intercepts include:
o 12m @ 1.9 g/t Au from 47m and 9m @ 1.00 g/t from 68m (DVC002)
o 9m @ 0.95 g/t Au from 73m (DVC003)
o 6m @ 1.12 g/t Au from 53m (DVC008)
o 4m @ 1.14 g/t Au from 66m (DVC012)
• No follow-up exploration has been completed at Devils Playground drill intercepts and no modern
geochemical or geophysical exploration undertaken since drilling was completed over 20 years ago.
• In addition, mining leases M15/1818 and M15/1352 cover multiple historical prospects at Bell Bird,
Tartan, Burbanks Welcome and Aurifer, with no modern exploration or drilling completed.
• Ore’s exploration programmes are progressing steadily at the Coolgardie Gold Projects with regional
Aircore (AC) drilling at the Burbanks East Gold Project (Burbanks East) now complete.
• AC drilling has commenced at Miriam, targeting key regional prospects including Jungle, Forrest North,
Burbanks Monarch and Goroke.
• Ore is well funded and strongly positioned to advance all planned exploration programmes across its
Goldfields portfolio, with a robust cash balance of A$9.6 million and zero debt (as at 31 March 2026).
oreresources.com.au 2
Ore Resources’ Managing Director and CEO, Nick Rathjen, commented:
“The execution of this binding option agreement represents an additional value growth lever for our business,
enabling the strategic consolidation of additional tenure that fills the key gaps in our current Miriam gold
footprint, creating one single, contiguous landholding.
“Importantly, the Agreement secures 4 granted mining leases, with two located immediately east of and
adjacent to Forrest, enabling us to undertake step-out drilling to test extensions to the emerging multi-lode gold
system further to the east. Although historical drilling data is limited, the new tenure demonstrates encouraging
indications of gold mineralisation, particularly at the Devils Playground prospect, a 300m long mineralised trend
situated on the eastern flank of the Miriam Shear. This highlights the potential for future drilling to unlock linking
structures between these two mineralised zones.
“Additionally, the Agreement includes two contiguous mining leases in the north of Miriam, which host multiple
underexplored prospects including Bell Bird, Tartan, Burbanks Welcome and Aurifer. These prospects remain
largely untested by modern exploration, providing significant potential for new high-impact gold discoveries
through detailed desktop evaluation and first-pass exploration drilling.
“The inclusion of this tenure adds significant new gold prospectivity at Miriam, supporting additional target
generation to the north and east, and sets the stage for longer-term, follow-up regional drilling at Miriam for
later in 2026 and beyond.”
Further consolidation of Miriam gold tenure
Ore has signed a binding option agreement with vendors, Mr Lance Fraser, Mr Graeme Tarabini and Mr Brett
Scott, providing it with an option to acquire four (4) mining leases, one prospecting licence application and one
special prospecting licence application covering highly prospective exploration tenure adjacent to its current
Miriam project landholdings.
Table 1: Summary details of the four mining leases and two prospecting licence applications
Tenement ID Area Ha Status
M15/1255 9.69 Granted
M15/1819 4.85 Granted
M15/1818 9.66 Granted
M15/1352 5.15 Granted
P15/5768-S 9.7 Application
P15/5775 5.5 Application
Total Area (ha) 44.55
The acquisition of this new tenure would further consolidate the Company’s existing Miriam tenure footprint,
unlocking prospective new ground directly adjacent to Ore’s flagship discovery at Forrest, on the eastern flank
of the 6.2km-long Miriam Shear Zone, and in the north of the project tenure complementing existing key
regional prospects (Figure 1).
oreresources.com.au 3
Figure 1: Miriam Project plan view including the four granted Mining Leases covered by the Agreement
Two mining leases (M15/1255 and M15/1819) are located directly east of and contiguous with the Forrest
prospect, the Company’s flagship deposit at Miriam (Figure 2).
Limited historical exploration has been conducted at M15/1255, where drilling was conducted in 2002 for a
total of 12 shallow reverse circulation (RC) holes. Despite the limited scope, this drilling defined consistent
gold mineralisation, with all drill traverses intersecting gold mineralisation across a 300m north–south (N–S)
strike extent (Figure 3).
oreresources.com.au 4
The tenement overlies the historic Devils Playground prospect which consists of historic shafts and surface
workings, likely dating from the Coolgardie Gold Rush (post-1892). The drilling conducted on this tenement
highlights a 300m long mineralised trend on the eastern flank of the Miriam Shear Zone.
Key historical intercepts from Devils Playground include:
• 12m @ 1.9 g/t Au from 47m (DVC002)
• 9m @ 0.95 g/t Au from 73m (DVC003)
• 6m @ 1.12 g/t Au from 53m (DVC008)
• 4m @ 1.14 g/t Au from 66m (DVC012)
These results highlight the prospectivity of the eastern flank of the Miriam Shear Zone for further gold
mineralisation, including the potential for parallel lodes and linking structures.
Figure 2: Forrest prospect – plan view with new tenure and historical drill intercepts
oreresources.com.au 5
Figure 3: Forrest – Devils Playground prospect – schematic cross section with new tenure and historical drill
intercepts
No recorded drilling has been completed at M15/1819, M15/1818 or M15/1352, which are located to the
north of M15/1255. However, both M15/1818 and M15/1352 host several documented gold occurrences
recorded in the MINEDEX database, including the Bell Bird, Tartan, Burbanks Welcome, and Aurifer prospects.
Preliminary field investigations have confirmed the presence of historical gold workings and shafts across
these tenements, along with evidence of more recent near-surface gold exploitation. The lack of systematic
modern exploration, including drilling and geophysical surveys, highlights the underexplored nature of this
tenure and supports its potential for further gold discoveries utilising Ore’s proven, low-cost exploration
strategy.
The option agreement also includes two prospecting licence applications. P15/5768-S is a special prospecting
licence application, which grants the right to conduct surface gold exploration to a depth of 50m. P15/5775 is
a prospecting licence application located approximately 750m north of Miriam (Figure 1) and contiguous with
Maritana Minerals’ (ASX: MRT) Burbanks deposit (466 koz @ 2.4 g/t Au)0F0F
1
.
The grant of these licences will be subject to the submission and approval of a Reserve Activity Management
Plan.
Agreement terms
The material terms of the Agreement between the Company and vendors, Mr Lance Fraser, Mr Graeme
Tarabini and Mr Brett Scott, are as follows:
• Option: Exclusive option period of three months in consideration for the payment of an upfront, non-
refundable option fee of A$50,000 cash.
• Exercise: If the option is exercised, payment of A$500,000 in the form of A$300,000 cash and the
remaining A$200,000 paid in OR3 scrip priced at the 5-day VWAP immediately prior to the date of
exercise of the option, with a 6 month voluntary escrow period.
1 For full details on Burbanks, refer to Maritana Minerals Ltd (ASX: MRT) Reserves & Resources
oreresources.com.au 6
In the event the option is exercised, settlement of the acquisition will be subject to customary conditions. The
Agreement otherwise contains terms and conditions considered standard for agreements of this nature.
Next steps
This additional tenure provides a compelling opportunity to enhance the Company’s gold exploration portfolio
and complement planned and ongoing exploration programmes across the Coolgardie Gold Projects.
With much of the acquiredground comprising granted mining leases, Ore is well positioned to rapidly commence
exploration activities at this new tenure. Subject to exercise of the option and the successful completion of the
transaction, Ore plans to commence exploration of this new tenure following the completion of requisite
heritage surveys and the approval of a Programme of Work (PoW).
Figure 4: Coolgardie Gold Projects – Location Map
oreresources.com.au 7
This announcement has been authorised for release by the Board of Directors of the Company.
For further information, visit http://www.oreresources.com.au/ or contact:
Nicholas Rathjen Robin Cox
CEO & Managing Director Technical Director
E: nrathjen@oreresources.com.au E: rcox@oreresources.com.au
https://oreresources.com.au/link/PKv37r
Competent Persons Statement
The information in this announcement that relates to Exploration Results pertaining to the tenements the subject
of the Agreement is based on and fairly represents information compiled by Mr Robin Cox BSc (E.Geol), a
Competent Person, who is a Member of the Australian Institute of Mining and Metallurgy. Mr Cox is the
Company’s Chief Geologist and has sufficient experience that is relevant to the style of mineralisation and type
of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined
in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves. Mr Cox consents to the inclusion in this announcement of the matters based on his information in the
form and context in which it appears.
Forward-Looking Statements
This document may include forward-looking statements. Forward-looking statements include, but are not limited
to, statements concerning Ore Resources Limited’s planned exploration programme and other statements that
are not historical facts. When used in this document, the words such as “could,” “plan,” “estimate,” “expect,”
“intend,” “may”, “potential”, “should,” and similar expressions are forward-looking statements. Although Ore
Resources Limited believes that its expectations reflected in these forward-looking statements are reasonable,
such statements involve risks and uncertainties, and no assurance can be given that actual results will be
consistent with these forward-looking statements.
Previously Reported Results
The information in this announcement that relates to previously reported Exploration Results is extracted from
the ASX announcements dated 23 April 2026, 15 April 2026, 9 April 2026, 20 January 2026, 24 November 2025,
10 November 2025, 15 September 2025, 2 September 2025 and 27 May 2025 (Original Announcements), as
referenced, which are available at www.oreresources.com.au. Ore confirms that it is not aware of any new
information or data that materially affects the information included in the Original Announcements and, that all
material assumptions and technical parameters underpinning the estimates in the Original Announcements
continue to apply and have not materially changed. Ore confirms that the form and context in which the
Competent Persons’ findings are presented have not been materially modified from the original announcement.
oreresources.com.au 8
About Ore Resources Ltd (ASX:OR3)
THE BUSINESS: Gold and lithium exploration and development
Ore Resources (ASX: OR3) is an exploration and development company focused on rapidly advancing its 100%
owned Coolgardie and Kal East Gold and Lithium Projects in the Eastern Goldfields of Western Australia.
THE LOCATION: Infrastructure-rich project setting
The Eastern W.A. Goldfields is an
outstanding location in which to explore
for, build, and operate gold and lithium
mines. It is a long-established mining
province with all the accompanying
benefits, including all-year land access,
skilled labour, mining services and
infrastructure.
The Projects are positioned within 50km of
the mining hub of Kalgoorlie (via sealed and
access roads), approximately 370km to the
port of Esperance and approximately
550km to Perth via road and rail. We are
proximal to multiple gold and lithium
mining and processing operations and
development projects of substantial scale.
This available range of potential
commercialisation options, including
standalone development, positions us well
to monetise current and future success.
THE TEAM: Proven value generators
Our carefully assembled team has an extensive track record of exploration success, project stewardship,
development expertise and operating excellence that has repeatedly resulted in the delivery of substantial
shareholder value: Nick Rathjen (MD), Robin Cox (Technical Director), Nev Power (Chairman), Rob Waugh (NED).
THE CAPACITY: Balance sheet strength and runway
We are a business and team that is resolutely focussed on the stewardship of our shareholders’ capital and the
astute application of this capital for maximal return. We are well-funded to undertake our extensive planned
exploration and evaluation work programs throughout 2026 and beyond.
oreresources.com.au 9
Table 2 - Significant Intercepts >0.3g/t Au
(Historic Exploration)
Hole ID
From
(m) To (m)
Width
(m)
Grade
Au g/t Intercept
Gram x
Metre
DVC001 52 53 1 0.38 1m @ 0.38g/t Au 0.38
DVC002 47 59 12 1.9 12m @ 1.9 g/t Au 22.8
DVC002 68 77 9 1.00 9m @ 1.00g/t Au 9
DVC003 73 82 9 0.95 9m @ 0.95 g/t Au 8.55
DVC004 47 48 1 1.07 1m @ 1.07g/t Au 1.07
DVC005 NSI
DVC006 NSI
DVC007 16 18 2 1.47 2m @ 1.47g/t Au 2.94
DVC008 53 59 6 1.12 6m @ 1.12g/t Au 6.72
DVC009 NSI
DVC010 23 27 4 0.77 4m @ 0.77g/t Au 3.08
DVC011 33 37 4 0.6 4m @ 0.6g/t Au 2.4
DVC012 66 70 4 1.14 4m @ 1.14g/t Au 4.56
Table 3 Drill Hole Location Information
UTM MGA94 Zone 51
Hole ID
Hole
Type
Max
Depth
(m) Easting Northing RL Dip Azimuth
DVC001 RC 83 320139 6562938.1 418.37 -60 270
DVC002 RC 84 320160 6562936 419.196 -60 270
DVC003 RC 120 320182.7 6562936.4 419.958 -60 270
DVC004 RC 84 320185.3 6563018.7 421.167 -60 270
DVC005 RC 84 320197.5 6563018.4 421.422 -60 270
DVC006 RC 54 320084.1 6562854.6 415.829 -60 270
DVC007 RC 78 320123 6562853.4 416.574 -60 270
DVC008 RC 90 320149.2 6562854.2 418.039 -60 270
DVC009 RC 50 320062 6562787.8 416.486 -60 270
DVC010 RC 78 320100.5 6562787 417.369 -60 270
DVC011 RC 84 320083 6562720.4 414.153 -60 270
DVC012 RC 84 320103.2 6562720.4 415.588 -60 270
oreresources.com.au 10
JORC Code, 2012 Edition, Table 1
Section 1: Sampling Techniques and Data
CRITERIA EXPLANATION COMMENTARY
Sampling
techniques
• Nature and quality of sampling (eg cut
channels, random chips, or specific
specialised industry standard
measurement tools appropriate to the
minerals under investigation, such as
down hole gamma sondes, or handheld
XRF instruments, etc). These examples
should not be taken as limiting the broad
meaning of sampling.
• Include reference to measures taken to
ensure sample representivity and the
appropriate calibration of any
measurement tools or systems used.
• Aspects of the determination of
mineralisation that are Material to the
Public Report. In cases where ‘industry
standard’ work has been done this would
be relatively simple (eg ‘reverse
circulation drilling was used to obtain 1m
samples from which 3kg was pulverised
to produce a 30g charge for fire assay’).
In other cases more explanation may be
required, such as where there is coarse
gold that has inherent sampling
problems. Unusual commodities or
mineralisation types (eg submarine
nodules) may warrant disclosure of
detailed information.
• Reverse Circulation drilling collects a 1m
bulk sample. A 2-3kg sample is cone split
from the drill rig and collected in a pre-
marked calico bag. 4m composites
samples are collected proportionally via
spear from the 1m bulk sample. Both 1
metre and 4 metre composites are
selected for fire assay purposes
producing a 50g homogenised split for
assay.
Drilling
techniques
• Drill type (eg core, reverse circulation,
open-hole hammer, rotary air blast,
auger, Bangka, sonic, etc) and details
(eg core diameter, triple or standard
tube, depth of diamond tails, face-
sampling bit or other type, whether core
is oriented and if so, by what method,
etc).
• Reverse Circulation uses 5.5 inch
pneumatic hammer to pulverise oxidised
and fresh rock which is then delivered to
the cyclone and cone splitter via
compressed air.
Drill sample
recovery
• Method of recording and assessing core
and chip sample recoveries and results
assessed.
• Measures taken to maximise sample
recovery and ensure representative
nature of the samples.
• Whether a relationship exists between
sample recovery and grade and
whether sample bias may have
occurred due to preferential loss/gain of
fine/coarse material.
• Bulk sample recovery was
measured/commented in sample logs.
• No sample bias relationship has been
identified.
Logging • Whether core and chip samples have
been geologically and geotechnically
logged to a level of detail to support
appropriate Mineral Resource
• Drill holes have been geologically logged
by geologists in the field, recording
oreresources.com.au 11
estimation, mining studies and
metallurgical studies.
• Whether logging is qualitative or
quantitative in nature. Core (or costean,
channel, etc) photography.
• The total length and percentage of the
relevant intersections logged.
lithology, oxidation, weathering, texture,
structure and mineralogy
• Geological data has been recorded on
Ore database. Logging is a qualitative
nature.
Sub-sampling
techniques and
sample
preparation
• If core, whether cut or sawn and
whether quarter, half or all core taken.
• If non-core, whether riffled, tube
sampled, rotary split, etc and whether
sampled wet or dry.
• For all sample types, the nature, quality
and appropriateness of the sample
preparation technique
• Quality control procedures adopted for
all sub-sampling stages to maximise
representivity of samples.
• Measures taken to ensure that the
sampling is representative of the in-situ
material collected, including for instance
results for field duplicate/second-half
sampling.
• Whether sample sizes are appropriate
to the grain size of the material being
sampled.
• Sampling of drill chips included
compositing by spear sample on 4m
composites.
• Single metre samples were cone split to
obtain an approximate 2-3kg sample.
• Certified reference material, including
known standards and blank material are
inserted at a rate of 1 in 20 for primary
samples, field duplicates are collected at
1 in 30.
• Analysis of QA/QC results is undertaken
by the company and external consultants
to ensure sampling accuracy.
•
Quality of assay
data and
laboratory tests
• The nature, quality and appropriateness
of the assaying and laboratory
procedures used and whether the
technique is considered partial or total.
• For geophysical tools, spectrometers,
handheld XRF instruments, etc, the
parameters used in determining the
analysis including instrument make and
model, reading times, calibrations
factors applied and their derivation, etc.
• Nature of quality control procedures
adopted (eg standards, blanks,
duplicates, external laboratory checks)
and whether acceptable levels of
accuracy (i.e. lack of bias) and precision
have been established.
• Sipa Resources conducted RC (12
holes) drilling between 2002 and 2007.
Samples were assayed by Ultratrace
laboratories utilising methods, ICP101,
ICP102, ICP302 and fire assay FA002
and FA003
• Qa/Qc results are acceptable
Verification of
sampling and
assaying
• The verification of significant
intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data
entry procedures, data verification, data
storage (physical and electronic)
protocols.
• Discuss any adjustment to assay data.
• Significant intercepts are calculated by
database algorithm and verified by Ore
staff and Database contractors.
• All field data is imported to the Ore
geochemistry database utilising industry
data logging software LogChief. This is
uploaded to sequel server database
hosted on Maxwell Geoservices
proprietary software and managed for
Ore by an external database company
Mitchell River Group Pty Ltd.
• No adjustments are made to assay data
• Gold significant intercepts are calculated
using a 0.3g/t lower cut off.
• Grade by metre calculations are a simple
multiplication of the gold grade by the
oreresources.com.au 12
width of the intercept and this is used to
weight the significance of an intercept.
• Ore twinned selective historic drill holes
of identified lodes to determine accuracy
of historic results.
Location of data
points
• Accuracy and quality of surveys used to
locate drill holes (collar and down-hole
surveys), trenches, mine workings and
other locations used in Mineral
Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic
control.
• Drill Holes were surveyed utilising a GPS
with 5m accuracy including elevation
• All drill hole collar information has been
supplied and projected to UTM MGA 94
Zone 51
Data spacing
and distribution
• Data spacing for reporting of
Exploration Results.
• Whether the data spacing and
distribution is sufficient to establish the
degree of geological and grade
continuity appropriate for the Mineral
Resource and Ore Reserve estimation
procedure(s) and classifications
applied.
• Whether sample compositing has been
applied.
• At Devils Playground M15/1255holes
were drilled on 30m spacing, 90m line
spacing.
• Data spacing is appropriate for identifying
continuous and non-continuous
geochemical anomalies and future
Mineral Resource estimates.
Orientation of
data in relation
to geological
structure
• Whether the orientation of sampling
achieves unbiased sampling of possible
structures and the extent to which this is
known, considering the deposit type.
• If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to
have introduced a sampling bias, this
should be assessed and reported if
material.
• Drilling has been conducted on E-W grid
lines. Geological units in the region have
a dominantly N-S to NE-SW strike. As
such the E-W drilling provides relative
oblique interceptions.
• Drilling intercepted both oxide/supergene
mineralisation and fresh bedrock
intercepts. More drilling is required to
better determine the dip and direction of
the fresh bedrock gold mineralisation.
Sample security • The measures taken to ensure sample
security.
• Reported Samples are historic, sample
security measures of Sipa Resources in
2002 is unknown.
Audits or
reviews
• The results of any audits or reviews of
sampling techniques and data.
No independent audit or review has been
undertaken.
Section 2: Reporting of Exploration Results
CRITERIA EXPLANATION COMMENTARY
Mineral tenement
and land tenure
status
• Type, reference name/number, location
and ownership including agreements or
material issues with third parties such
as joint ventures, partnerships,
overriding royalties, native title
interests, historical sites, wilderness or
national park and environmental
settings.
• The new tenements under the
option agreement consist of
M15/1255, M15/1819, M15/1818
M15/1352 and applications
P15/5775 and P15/5768-S
• The tenements are located in the
Kangaroo Hills Timber Reserve, an
approved Conservation
oreresources.com.au 13
• The security of the tenure held at the
time of reporting along with any known
impediments to obtaining a licence to
operate in the area.
Management Plan permits
conditional access and exploration
of the tenure.
• The tenements are in good standing
and no known impediments exist.
Exploration done
by other parties
Acknowledgment and appraisal of
exploration by other parties.
The Historic data represented in this
announcement was culminated from the
exploration work conducted the following
parties.
• Sipa Resources conducted RC (12
holes) drilling between 2002 and
2007. Samples were assayed by
Ultratrace laboratories utilising
methods, ICP101, ICP102, ICP302
and fire assay FA002 and FA003
•
Geology Deposit type, geological setting and style of
mineralisation.
• The Miriam project is prospective for
Lithium, Caesium, Tantalum (LCT)
enriched pegmatites which intrudes
older Archean aged greenstone
lithologies.
• The tenements are prospective for
lode and structurally hosted gold
mineralisation hosted within Archean
aged greenstone lithologies.
Drill hole
Information
• A summary of all information material
to the understanding of the
exploration results including a
tabulation of the following information
for all Material drill holes:
• easting and northing of the drill hole
collar
• elevation or RL (Reduced Level –
elevation above sea level in metres)
of the drill hole collar
• dip and azimuth of the hole
• down hole length and interception
depth
• hole length.
• If the exclusion of this information is
justified on the basis that the
information is not Material and this
exclusion does not detract from the
understanding of the report, the
Competent Person should clearly
explain why this is the case.
• Drill Hole collar tables including
location, height and drill direction have
been included. (Table 2).
• Significant intercepts are specified as
down hole lengths.
• Maximum Au assay has been
represented in the maps. This data is
included in the collar table
• Significant intercept assay data has
been tabled. (Table1)
Data aggregation
methods
• In reporting Exploration Results,
weighting averaging techniques,
maximum and/or minimum grade
truncations (eg cutting of high grades)
and cut-off grades are usually
Material and should be stated.
• Where aggregate intercepts
incorporate short lengths of high-
grade results and longer lengths of
low-grade results, the procedure used
for such aggregation should be stated
and some typical examples of such
• Grade by metre iconology have been
included in maps. Cutoff ranges are
shown in legends
• Significant intercepts are considered
as intercepts >0.3g/t Au and include
up to 2m internal dilution. This is
considered a significant intercept for
a known gold bearing system.
• Significant intercepts which include
both 1m samples and 4 metre
composites are calculated via a
length weighted average.
oreresources.com.au 14
aggregations should be shown in
detail.
• The assumptions used for any
reporting of metal equivalent values
should be clearly stated.
Relationship
between
mineralisation
widths and
intercept
lengths
• These relationships are particularly
important in the reporting of Exploration
Results.
• If the geometry of the mineralisation
with respect to the drill hole angle is
known, its nature should be reported.
• If it is not known and only the down
hole lengths are reported, there should
be a clear statement to this effect (eg
‘down hole length, true width not
known’).
• All results are reported as down hole
length only. Mineralisation is
interpreted as semi-vertical lodes
however geological understanding is
still insufficient and further drilling
planned by Ore aims to address the
uncertainty.
Diagrams Appropriate maps and sections (with
scales) and tabulations of intercepts should
be included for any significant discovery
being reported These should include, but
not be limited to a plan view of drill hole
collar locations and appropriate sectional
views.
Relevant diagrams have been included
within the announcement.
Balanced
reporting
Where comprehensive reporting of all
Exploration Results is not practicable,
representative reporting of both low and
high grades and/or widths should be
practiced to avoid misleading reporting of
Exploration Results.
• Assay data has been represented for
all holes drilled in the project area
including holes with no significant
intercept.
Other
substantive
exploration data
Other exploration data, if meaningful and
material, should be reported including (but
not limited to): geological observations;
geophysical survey results; geochemical
survey results; bulk samples – size and
method of treatment; metallurgical test
results; bulk density, groundwater,
geotechnical and rock characteristics;
potential deleterious or contaminating
substances.
No other substantive data exists.
Further work • The nature and scale of planned further
work (eg tests for lateral extensions or
depth extensions or large-scale step-
out drilling).
• Diagrams clearly highlighting the areas
of possible extensions, including the
main geological interpretations and
future drilling areas, provided this
information is not commercially
sensitive.
• Ore is awaiting Diamond Core drilling
Results
• Ore is currently conducting a regional
Air Core drilling programme of the
Coolgardie Gold Project
• Ore will conduct further drill testing of
the Miriam project which is scheduled
for Q3 2026.
• Refer to figures/diagrams in the main
body of text.