LITHIUM DSO STUDY POSITIONS KANGAROO HILLS FOR
RAPID LITHIUM PRODUCTION AND CASH FLOW
Ore Resources Ltd (ASX: OR3) (Ore or the Company) is pleased to announce the results of the Scoping Study
(Study) for its 100%-owned Kangaroo Hills Lithium Project (Kangaroo Hills or the Project), part of its broader
Coolgardie Lithium Projects located in the Eastern Goldfields of Western Australia.
The Study demonstrates the robust technical viability and strong forecast economic outcomes of a capital-lite,
rapid-deployment operation at Kangaroo Hills, involving the open pit mining, crushing, trucking and export of
lithium-bearing pegmatite ore under a Direct Shipped Ore (DSO) arrangement. It delivers a compelling
assessment of Kangaroo Hills' development potential and establishes a strong platform for rapid execution.
The release of the Study coincides with the declaration of an initial Mineral Resource (MR) for Kangaroo Hills,
comprising 3.10 Mt at 1.01% Li2O for 31,200 t contained Li2O (at a 0.40% Li₂O cut-off).
Study - Key Physical Parameters Unit LOM
Total material mined Mt 11.1
Mine life Months 16
Strip ratio waste: ore 7.9
Recovery % 95
Total DSO production Mt 1.19
Average DSO product grade % Li2O 1.07
Operating cost per DSO tonne (incl royalties) A$/t CIF 210
Lithium DSO price input A$/t CIF 430
Capital cost A$M 24.9
NPV8% (pre-tax, real basis) A$M 220.8
IRR (pre-tax, real basis) % 4,995
Net cash flow (post capital, pre-tax) A$M 237.5
Project commencement to first DSO production Months < 2
Payback (pre-tax) from project commencement Months < 4
The Project enables rapid free cash flow generation while supporting the potential longer-term development
of a standalone spodumene concentrate operation. Subject to receipt of requisite approvals and finalisation of
project funding, a Final Investment Decision (FID) on the Project is targeted for mid-2027.
FURTHER POTENTIAL UPSIDE DRIVERS
• Substantial excluded material. In favour of a low-strip low-opex development, 1.14 Mt of DSO material
(Indicated) within the economic pit shell was excluded from the Study production schedule; sustained
elevated prices would see this material readily mined and sold to significantly extend initial operating life.
• Process optimisation, including ore sorting, to drive additional pricing and cost efficiencies.
• Domestic ore sales to lithium process plants in Western Australia (in alternative to DSO).
• Resource growth and new discovery(s) at Kangaroo Hills (Big Red/Rocky/Potoroo pegmatite system
remains open along strike and at depth) and the neighbouring Miriam Lithium Project.
• Tantalum by-product recovery and sale.
oreresources.com.au 2
NEXT STEPS AND KEY CATALYSTS
• Funding. Discussions advancing with potential strategic and commercial offtake partners, targeting a non-
dilutive prepayment funding solution for the low upfront capital cost of the Project.
• Approvals. Finalisation of Mining Licence grant and rapid progression though requisite environmental
approvals; Project Agreement already in place with Marlinyu Ghoorlie.
• Further de-risking and optimisation. Additional ore sorting, metallurgy and geotechnical workstreams in
support of rapid development execution planning.
• Growth-focussed exploration. Further drilling programs planned across Kangaroo Hills and Miriam
designed to target resource growth and new discovery(s) across this underexplored lithium tenure.
Cautionary Statements
The Scoping Study referred to in this ASX release has been undertaken for the purpose of initial evaluation of a potential
development of the Kangaroo Hills Lithium Project. The Study is preliminary in nature and is based on low-level technical
and economic assessments that are insufficient to support the estimation of Ore Reserves or to provide assurance of an
economic development case at this stage. Further evaluation work and appropriate studies will be required before the
Company is able to establish the economic viability of the Project. Given the uncertainties involved, investors should not
make any investment decisions based solely on the results of the Scoping Study.
Of the Mineral Resources scheduled for extraction in the Scoping Study mine plan, 100% are classified as Indicated. The
Mineral Resources underpinning the production target in the Scoping Study have been prepared by a competent person in
accordance with the requirements of the JORC Code (2012). The Competent Person’s Statement can be found at the
conclusion of this ASX release. Ore confirms that it is not aware of any new information or data that materially affects the
information pertaining to this release.
This document contains a series of forward-looking statements. Forward-looking statements include, but are not limited to,
statements concerning Ore’s planned exploration and development activities and other statements that are not historical
facts. When used in this document, the words such as “could,” “plan,” “estimate,” “expect,” “intend,” “may”, “potential”,
“should,” and similar expressions are forward-looking statements. Although Ore believes that its expectations reflected in
these forward-looking statements are reasonable, such statements involve risks and uncertainties, and no assurance can be
given that actual results will be consistent with these forward-looking statements.
Ore has concluded that it has a reasonable basis for providing these forward-looking statements and the forecast financial
information included in this release. This includes a reasonable basis to expect that it will be able to fund the development
of the Kangaroo Hills Lithium Project upon successful delivery of the requisite development milestones, when required. The
reasons for these conclusions are outlined throughout this ASX release. While Ore considers all of the material assumptions
to be based on reasonable grounds, there is no certainty that the Company will be able to successfully finance, construct or
operate the Project. There is no certainty that the Company will be able to convert Mineral Resources to Ore Reserves, secure
all necessary approvals, obtain required financing, establish commercial offtake arrangements or achieve the operational
performance assumed in the Study.
The Scoping Study is based on material assumptions that include third-party factors over which the Company has little or
no control. Actual results may differ materially from those currently anticipated. Accordingly, investors should not place
undue reliance on the production target, forecast financial information or conclusions contained in the Scoping Study when
making investment decisions.
No Ore Reserve has been declared. This ASX release has been prepared in compliance with the current JORC Code (2012)
and the ASX Listing Rules. All material assumptions, including sufficient progression of all JORC modifying factors on which
the production target and forecast financial information are based, have been included in this ASX release.
oreresources.com.au 3
Ore Resources’ Managing Director and CEO, Nick Rathjen, commented:
"On behalf of the team at Ore Resources, I am delighted to present this capital-lite and short-lead production
plan for the Kangaroo Hills Lithium Project. The Study demonstrates that a contractor-led DSO development
pathway at Kangaroo Hills offers a low-cost, rapid pathway to substantial free cashflow generation,
underpinned by robust technical and operating outcomes.”
“By leveraging contract mining, crushing and logistics services, the proposed development minimises upfront
capital requirements, shortens implementation timelines and delivers attractive project economics.
Importantly, the speed to market offered by the DSO approach aligns strongly with current lithium market
conditions. This operating model generates a strong projected operating margin at modest pricing assumptions
and delivers a quick payback, highlighting the potential for rapid cash generation and value creation.”
“The outcomes of this Study are underpinned by the declaration of an initial Mineral Resource for Kangaroo
Hills, a key milestone representing the culmination of more than 38,000m of RC, Air Core and diamond drilling
completed since the discovery of lithium mineralisation in 2022.”
"The DSO opportunity presents both a rapid pathway to early cash flow generation and an important first step
in the future resource growth opportunity at Kangaroo Hills. We have already identified several opportunities
to further optimise the project and enhance value through additional study, efficiency and resource growth
initiatives.”
"The Scoping Study mine plan is based entirely on Indicated Mineral Resources and excludes oxide material,
providing a higher level of confidence in the projected production profile. The chosen pit design balances
stripping requirements and operating cost, also supporting a streamlined pathway to project execution. This
means that a further approximately 1.0 Mt of mineralised material within the broader economic pit shell was
excluded from the Study production schedule, representing a significant opportunity for future pit expansion
and mine life extension.”
"In addition to lithium, the Mineral Resource contains an average grade of 118 ppm Ta₂O₅, comparing strongly
with several regional lithium operations that produce tantalum concentrates as a by-product. This multi-
commodity potential reflects an additional potential revenue stream which we intend to evaluate and unlock.”
"We also remain highly encouraged by the broader exploration potential across our Coolgardie Lithium
Projects. Further drilling programmes are set to target extensions to the Big Red, Rocky and Potoroo
pegmatites, while regional exploration at the Miriam Lithium Project will seek to define new lithium discoveries
and resources that could further enhance the scale of operations.”
"Looking ahead, we are driving towards rapid development of Kangaroo Hills. A range of technical
workstreams, including geotechnical investigations, detailed metallurgical testwork and the assessment of ore
sorting opportunities at Big Red, are aimed at further optimising project outcomes and reducing risk. In
parallel, we are advancing Mining Lease grant and requisite environmental approval processes. We are also
progressing discussions with potential strategic and commercial partners for a simple, non-dilutive finance
arrangement to fund this initial development of Kangaroo Hills.”
"The robust outcomes of the Study provide a strong platform for continued engagement with all key
stakeholders for Kangaroo Hills. We look forward to rapidly moving towards execution on this short-lead
lithium development opportunity, with the size of the economic opportunity on offer being abundantly clear
from the Study outcomes presented herein. Final Investment Decision, prompt project commencement and first
DSO production are targeted for mid-2027.”
oreresources.com.au 4
Executive Summary
The Study proposes a low-capital, speed-to-market development at Kangaroo Hills centred around a simple
mining, crushing and DSO export strategy. The Study was completed by leading engineering and technical
consultant, Sedgman Pty Ltd, with an estimation accuracy of ±35%.
The Study assessed the full project value chain, from mining through to product export, and was completed to
an AACE Class 5 Scoping Study standard. The assessment defined key infrastructure requirements, operating
assumptions, capital and operating costs, and project economics.
Under the proposed development strategy, ore is to be mined from Kangaroo Hills, processed through a
crushing circuit and transported 380km via road haulage to the Port of Esperance for export as a bulk DSO
product to international offtake partners on a CIF basis. By producing a DSO product, the Project avoids the
significant capital expenditure, technical complexity and extended construction schedules typically associated
with development of concentrate processing facilities.
A contractor-led development model has been adopted to minimise upfront capital expenditure, reduce
execution risk and accelerate the pathway to production. Under this assumption, mine design and production
scheduling were completed based on a Run-of-Mill (ROM) mining rate of 750 ktpa and the production of a
spodumene-bearing DSO product through a simple crushing and screening flowsheet. Overall, the Study
forecasts total life of mine production of 1.19 Mt of DSO.
The Study outcomes highlight a robust and economically attractive standalone lithium operation, forecast to
generate A$513.4 million in revenue and A$237.5 million in net cash flow (post capital, pre-tax) over an initial
mine life of 16 months.
Table 1 – Key Physical Parameters
Key Physical Parameters Unit Value
Total material mined Mt 11.1
Plant throughput ktpa 750
Mine life months 16
Plant feed Mt 1.26
Total waste mined Mt 9.9
Strip ratio waste: ore 7.9
Plant recovery % 95
Average product grade (Li2O) % 1.07
Total DSO production Mt 1.19
oreresources.com.au 5
Table 2 – Key Financial Outcomes
Key Financial Outcomes Unit Value
Price assumptions
Lithium Carbonate price US$/t 24,500
Lithium DSO price (1% Li2O equivalent product) AS$/t 430
Project outcomes
Revenue A$M 513.4
Operating costs A$M 251.1
Capital costs A$M 24.9
Net cash flow (post capital, pre-tax) A$M 237.5
NPV8% (pre-tax, real) A$M 220.8
IRR (pre-tax, real) % 4,995%
Payback period (pre-tax) months 4
Project Background
Kangaroo Hills consists of more than 13.2km2
of highly prospective granted lithium tenure strategically located
along a key interpreted lithium trend within the Coolgardie Greenstone Belt. It is situated approximately 17km
south of the township of Coolgardie, within a tier-one mining jurisdiction renowned for its established utilities
and transport infrastructure, skilled workforce, and long operating history for both gold and lithium
production.
The Project benefits from proximity to existing infrastructure and processing capacity, including haul roads,
power, and nearby milling operations. Notably, Mineral Resources Ltd’s (ASX: MIN) Mt Marion lithium
operation is located approximately 30km to the east (50km via sealed road), underscoring the favourable
location within an active and well-supported lithium producing region.
oreresources.com.au 6
Figure 1: Kangaroo Hills Lithium Project – WA Regional Map
The Company has been actively exploring the Coolgardie region since 2021. Spodumene mineralisation within
lithium-caesium-tantalum (LCT) pegmatites was first discovered at Kangaroo Hills during regional exploration
drilling in late 2022. Subsequent drilling defined a near-surface, shallow dipping pegmatite system at Big Red
(and Rocky), characterised by thick, laterally continuous mineralisation and consistently strong lithium grades.
Significant exploration activities were completed at the Project over 2023-2024.
Geology and Mineralisation
Kangaroo Hills is located within the Archaean greenstones of the Coolgardie Domain in Western Australia's
Eastern Goldfields. Lithium mineralisation is hosted within spodumene-bearing LCT pegmatites, including the
Big Red/Rocky and Potoroo deposits, which comprise shallow north-dipping dykes and vein arrays with
oreresources.com.au 7
consistent geometry and mineralogy. Tantalum is also present within the system, and the Project is situated
within a well-established lithium district.
Metallurgical testwork completed in 2024 confirmed that spodumene is the dominant lithium-bearing mineral
within the Big Red deposit, accounting for greater than 90% of the contained lithium oxide (Li₂O). The testwork
further demonstrated that the ore is amenable to conventional beneficiation techniques, including Dense
Media Separation (DMS) and froth flotation processing.
Figure 2: Kangaroo Hills and Miriam Lithium Projects – Plan View
oreresources.com.au 8
Mineral Resources
An initial Mineral Resource has been declared for Kangaroo Hills, consisting of 3.10Mt at 1.01% Li2O and
118ppm Ta2O5 for contained metal of approximately 31,200 t Li2O and 804,200 lb Ta2O5.
Pursuant to ASX listing rule 5.8.1 and complementing JORC Table 1, Sections 1, 2 and 3 contained in the
annexures to this announcement, Ore provides the following summary in regard to the Mineral Resource
(MR). The MR is based on a drilling database comprising 261 drill holes for 38,229m, including 246 Reverse
Circulation (RC) holes for 38,166m, 18 diamond drill holes for 1,975m, and 13 aircore (AC) holes for 347m. Of
this comprehensive dataset, 98 drill holes totalling 15,123m were used to define the MR.
The key lithological and mineralisation contacts defining the pegmatite bodies were wireframed using the vein
and erosion modelling tools in Leapfrog™ Geo software, informed by geological logging of lithology,
mineralogy, alteration and structure in conjunction with Fe2O3, Li2O and Ta2O5 assay data. A total of eleven
discrete pegmatite domains (Figure ) were modelled, including internal high-grade spodumene-rich
subdomains within the Big Red (D01) and Rocky (D11) pegmatites, with wireframes exported to Dassault
Systèmes GEOVIA Surpac™ for block model construction.
Figure 3: Oblique view of the KHLP pegmatite vein system with imagery on topography
Bulk density testwork was completed by Ore Resources Limited using hydrostatic weighing on uncoated NQ
and HQ diamond core, comprising 513 samples in total, of which 174 fall within the modelled mineralised
pegmatite domains. Bulk density has been assigned according to oxidation state (2.60 t/m3
for oxide, 2.65
t/m3
for transitional and fresh mineralisation, and an average of 3.0 t/m3
for waste), with further
measurements to be collected from future drilling.
Geochemical Samples were sent to ALS Minerals in Perth, WA for analysis. Lithium samples were fused with
Na2O2 and digested in hydrochloric acid, the solution is analysed by ICP; laboratory package code ME-MS81 ICP-
AES, ME-MS91. The method is considered a whole rock analysis. The methods are considered suitable for the
oreresources.com.au 9
style of mineralisation targeted. A stoichiometric conversion of Li to Li2O is applied post data receipt consisting
of a factor of 2.153 and Ta to Ta2O5 consisting of a factor of 1.22.
Directional variography was completed by domain using traditional semi-variograms modelled in Surpac and
Isatis, with nugget values generally low to moderate-high (10-40%) and structure ranges of up to 75m. The
D01 (Big Red) domain, supported by the greatest number of composites, produced the best-structured
variogram, which was applied to the remaining domains with the exception of the internal high-grade
subdomains, which used the variogram derived from the D01_HG domain.
Grade estimation for Li2O, Ta and Fe2O3 was completed using Ordinary Kriging in GEOVIA Surpac™, constrained
within the eleven mineralised domains and their internal high-grade subdomains. A five-pass estimation
strategy was applied, with search distances expanding from 20m in the first pass to 120m and beyond in later
passes, and search ellipse orientations dynamically aligned to the strike and dip of each domain using
Leapfrog™ Edge's Variable Orientation tool.
To reflect the reasonable prospects of eventual economic extraction (RPEEE) as described by the JORC Code
(2012) the following has been considered:
• Tenure status
• Approvals process and status
• Environmental and broader regulatory approvals
• Mining options
• Metallurgical testwork results to date
• Processing flowsheet base options
Options on pricing were used to evaluate the RPEEE constraints with the reported Mineral Resource
constrained within an optimized pit shell that utilised a product price assumption of $650 AUD/t DSO.
The Competent Persons for the Mineral Resource, as per the requirements of the Joint Ore Reserves
Committee (JORC) 2012 Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves, for the KHLP resource are Lauritz Barnes (MAusIMM, MAIG) of Trepanier and Robin Cox (MAusIMM)
of Ore Resources Limited. Mr Barnes reviewed and refined the geological and mineralisation wireframes, and
completed the statistical analysis, variography, grade estimation and construction of the resource block
model. Robin Cox (MAusIMM) of Ore Resources Limited has been involved with the KHLP since 2021,
conducting regular site visits and managed the exploration, drilling, sampling and on-site work in support of
the resource estimate and this report.
The Kangaroo Hills MRE forms the basis of the Study and is reported above a 0.40% Li₂O cut-off grade.
Approximately 90% of the reported resource sits within the indicated category highlighting drill density
achieved to date.
oreresources.com.au 10
Yellow = Indicated, Light blue = Inferred & 0.4 % Li2O Cut Off
Figure 4: Oblique view of Indicated & Inferred Mineral Resource (non-RPEEE constrained)
Table 3 – Kangaroo Hills Mineral Resource Estimate (August 2026)
Category Tonnes (Mt)
Grade Contained Metal
Li2O % Ta2O5 ppm Fe2O3 % Li2O (t) Ta2O5 (lb)
Indicated 2.71 1.05 118 1.2 28,400 708,700
Inferred 0.38 0.74 113 1.6 2,800 95,500
Total 3.10 1.01 118 1.23 31,200 804,200
Note: Appropriate rounding applied.
Table 4 – Kangaroo Hills Mineral Resource Estimate (August 2026) by Oxidation Domain
Category Tonnes (Mt)
Grade Contained Metal
Li2O % Ta2O5 ppm Fe2O3 % Li2O (t) Ta2O5 (lb)
Transition 0.49 0.97 100 1.40 4,800 108,800
Fresh 2.60 1.02 121 1.20 26,400 695,400
Total 3.10 1.01 118 1.23 31,200 804,200
Note:
• MRE is reported above a Li2O cut-off grade of 0.40% within a optimised pit shell using appropriate mining and processing costs, recoveries and revenue values
• Mineral Resources are not Orel Reserves – Further detailed economic studies and additional modifying factors are required
• The Mineral Resource was classified following the guidelines presented in JORC Code 2012
• Appropriate rounding applied.
oreresources.com.au 11
Figure 5: Grade Tonnage Curve for the RPEEE lithium Mineral Resource
Mining
Under the Study, ore material will be open pit mined from the Big Red and Rocky pegmatites by a contract
mining fleet, hauled to a ROM stockpile and processed through a contractor-operated crushing facility to
produce a DSO product for export.
Utilising specialist contractors for all of mining, crushing and haulage operations delivers substantially reduced
owner capital requirements and avoids owner investment in large mobile fleets, crushing infrastructure,
maintenance facilities and operating personnel. This approach shifts a substantial proportion of project costs
from upfront capital expenditure to variable operating costs, reducing development risk and providing the
flexibility to align operating capacity with production requirements and prevailing market conditions.
oreresources.com.au 12
Figure 6: Kangaroo Hills Site Layout
oreresources.com.au 13
Figure 7: Kangaroo Hills Site Layout – Rendered Image
The open pit design has been developed based on a conventional mining fleet comprising 120-160 tonne
hydraulic excavators supported by 85-90 tonne haul trucks. The key design parameters adopted for the open
pit include:
• Ramp gradient of 1:9;
• Dual-lane haul ramps with a width of 25m;
• Single-lane haul ramps with a width of 15m;
• Minimum mining widths of 15m to 20m;
• Bench heights of 5m, mined in 2.5m flitches;
• Material movement is estimated to be in the range of 250,000 to 300,000 bcm per month;
• Passing bays incorporated within single-lane ramps where practicable; and
• Slope design parameters consistent with the geotechnical recommendations outlined in Table 5.
Pit wall configurations have been developed in accordance with geotechnical recommendations, with slope
angles and berm widths varying by depth to optimise both stability and economic recovery.
Table 5 – Geotechnical Parameters
Elevation Range (mRL) Bench Height (m) Batter Face Angle (°) Berm Width (m)
Above 390 10.0 55 6.0
390 to 380 10.0 60 6.0
Below 380 20.0 70 8.0
Note: The average surface RL is assumed to be 400m RL
oreresources.com.au 14
The proposed Big Red pit measures approximately 410m in length and 300m in width, with a maximum depth
of approximately 100m. In addition, a smaller satellite excavation, referred to as the Rocky pit, is planned
immediately south of Big Red and is expected to be developed to a depth of approximately 20m.
Figure 8: Plan View – Big Red and Rocky Pit Designs
oreresources.com.au 15
Figure 9: Kangaroo Hills – Resource Block Model
The selected mine design is based on an optimised pit shell (with a revenue factor of 0.54), which the
Company considers to deliver the most appropriate balance between ore inventory, strip ratio, mine life and
project economics, and reflects a lower-risk development strategy aligned with a near-term DSO operation. Pit
designs were carried out assuming mining dilution of 5%.
A larger optimisation shell, based on a revenue factor of 1.00, remains available for future development and
contains an additional approximately 1.0 Mt of plant feed, providing potential for mine life extension and
production growth. The current mine plan is sourced entirely from Indicated Mineral Resources, with no oxide
material included in the processing schedule. Mining activities are scheduled across an initial life of 16 months.
oreresources.com.au 16
Figure 10: Total Material Mined Schedule
Processing (Crushing)
The proposed crushing facility comprises a standalone modular operation located adjacent to the ROM
stockpile. The design is based on contractor proposals for processing lithium pegmatite ore at a nominal
throughput of approximately 750 ktpa. The circuit consists of a two-stage modular electric crushing and
screening plant configured to produce a final DSO product with a nominal P80 of 40 mm.
10
20
30
40
50
200
400
600
800
1,000
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Strip
Ratio
Total
Material
Mined
(kt)
Months
Ore Waste Strip Ratio
oreresources.com.au 17
Figure 11: Process Material Handling Flow
Under the proposed contracting model, the crushing contractor will supply, operate and maintain the crushing
plant, associated mobile equipment, power generation systems and supporting infrastructure. This approach
further minimises owner-funded capital expenditure and supports rapid mobilisation and commissioning.
Ore will be loaded into the crusher feed system using front-end loaders. Following primary crushing, material
will be screened, with oversize reporting to a secondary cone crusher for additional size reduction. The
screened material and secondary crusher product will then combine to form the final DSO stream, which will
be stacked onto the product stockpile via a radial stacker.
The selected primary crusher has capacity in excess of the required throughput, providing operational
flexibility and reducing the risk of production constraints arising from variations in ore characteristics
oreresources.com.au 18
Figure 12: DSO Production Schedule
Transport and Export Logistics
Crushed ore produced at Kangaroo Hills will be loaded from on-site stockpiles into contractor-operated road
trains and transported approximately 300km via sealed regional highways to a storage facility at the Port of
Esperance.
Road haulage offers several key advantages, including low capital requirements, operational flexibility, and
rapid implementation. Located approximately 17 km south of Coolgardie, Kangaroo Hills has direct access to
sealed regional highways connecting to Esperance and the broader Western Australian freight network.
This connection enables the use of conventional multi-trailer road trains and eliminates the need for
significant off-site capital works. Importantly, no dedicated loading facilities, rail sidings, or unloading
infrastructure are required, substantially reducing upfront capital expenditure relative to rail-based
alternatives.
Transport capacity can also be scaled efficiently with production and shipping requirements without requiring
significant infrastructure modifications. This approach is particularly well suited to the project's moderate
throughput and relatively short DSO mine life.
The Port of Esperance provides a well-established, low-capital pathway to export markets. The port currently
supports bulk commodity exports, including iron ore, grain, and mineral products, and has existing bulk
handling, storage, and ship-loading infrastructure.
The ability exists to utilise existing covered storage facilities and export infrastructure, subject to commercial
arrangements with Southern Ports and third-party logistics providers.
0.00%
0.20%
0.40%
0.60%
0.80%
1.00%
1.20%
30
60
90
120
150
180
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Li
2
O
grade
(%)
DSO
Produced
(kt)
Months
Big Red Rocky Li2O (%)
oreresources.com.au 19
Figure 13: Transport Logistics Map
Product Pricing and Marketing
For the purposes of the Study, Ore has adopted a battery-grade lithium carbonate price of US$24,500/t.
Applying a DSO pricing linkage of 1.25% and an A$/US$ exchange rate of 0.71 results in a forecast DSO price of
A$430/t CIF China over the mine life.
oreresources.com.au 20
Lithium DSO does not have a recognised published benchmark price and is typically priced by reference to
prevailing lithium carbonate or spodumene concentrate markets, with settlement adjusted for grade and
product quality. The adopted pricing assumptions are supported by market analysis and prevailing industry
pricing practices published by established research providers.
Offtake Marketing and Funding Strategy
Kangaroo Hills is currently unencumbered by offtake agreements, providing Ore with full flexibility to market
production either through spot sales or future offtake arrangements. Under the Study, DSO product will be
sold on a CIF basis, with Ore responsible for freight and delivery costs from the Port of